Home » CTS Departments » ConnectND » Campus Solutions » Campus Solutions 9.2 Upgrade Project

Campus Solutions 9.2 Upgrade Project

Project Quick Links

Purpose and Objectives | Charter | Project Organization Chart| Newsletters| Project Status | 9.2 Videos | 9.2 Documentation | 9.2 Advisory Group Info | 9.2 Glossary | 9.2 FAQs

February 2019 News

Campus Solutions 9.2 Advisory Group Meetings

Go to the 9.2 Advisory Group Info Quick Link above or here to view the recorded presentation and meeting materials. The next meeting is scheduled for March 28th.  The Advisory Group’s role is to be the campus voice on the Campus Solutions 9.2 project. The Project’s Communications Subcommittee is also still working on the best way to include faculty and students in initial design feedback.

Project Accomplishments

Feb 1             Sierra Cedar (SCI) consulting contract signed

Feb 22          Updated DEV Environment from PT 8.56.11/PUM 11 to PT 8.56.12/PUM 12

Feb 26          Test Environment available to BA/PA group – goal was Feb 15th

Feb 28          Updated DEMO Environment from PT 8.56.11/PUM 11 to PT 8.56.12/PUM 12

Mar 11           New version of ElasticSearch 6.1.2 deployed in TEST environment

Mar 13           Initial “New Look Coming” generic communication documentation released

Project Status – Test (TST) Environment Now Available!

The Test (TST) Environment has been released to the Programmers and Business Analysts so they can begin preliminary testing.  Campus Advisory Group members and those requesting access can review new features and functionality using NDUS data starting March 18th.  As of this moment, we still are targeting a July 12, 2019 Go-Live date.

Campus Solutions 9.2 Tentative Timeline

Mar 18                 Test Environment opened to Campus Advisory Group testers (4 weeks)

Mar 18 –Apr18   CTS Lunch and Learn Webinars for Campus Staff

April 15               NDUS How-To Documentation/Job Aids/Training Videos on website

April 26               Stage Environment Available

May 13- Jun 28  Testing for all users with Stage Environment access (7 weeks)

June 28                Production Freeze

July 2                    Go-No Go Meeting

Jul 12                   Go-Live Weekend. Production Environment Down at 5 pm Fri, up by noon Mon, July 15th

July 22                  Query Environment will be available (Working to improve date)

July 26                  Backup Go-Live Weekend. Production Environment Down noon Fri – 8 am Monday.