Home » CTS Departments » ConnectND » Campus Solutions » Campus Solutions 9.2 Upgrade Project

Campus Solutions 9.2 Upgrade Project

Project Quick Links

Purpose and Objectives | Charter | Project Organization Chart| Newsletters| Project Status | 9.2 Videos | 9.2 Documentation | 9.2 Advisory Group Info | 9.2 Glossary | 9.2 FAQs

May 2019 News

Campus Solutions 9.2 Advisory Group Meetings

Go to the 9.2 Advisory Group Info Quick Link above or here to view the recorded presentation and meeting materials. The next meeting is scheduled for May 30th.  The Advisory Group’s role is to be the campus voice on the Campus Solutions 9.2 project. The Project’s Communications Subcommittee is also still working on the best way to include faculty and students in initial design feedback.

Project Accomplishments

April             Lunch and Learn Presentations, Training Videos & Documentation Available

April 25        STAGE Environment available to BA/PA group – goal was April 26th

May 1            Campus On-Site Training Schedule Confirmed

May 13          STAGE Environment available to Campus users for testing

 

Project Status – Stage (STG) Environment Now Available!

The Stage (STG) Environment has been released to all Campus Stage users for testing effective May 13th.  As of this moment, we still are targeting a July 12-15, 2019 Go-Live outage.

Campus Solutions 9.2 Tentative Timeline

May 13- Jun 28  Testing for all users with Stage Environment access (7 weeks)

May 21                    STAGE Environment upgraded to PUM 13 (Similar to Bundle 53)

May 20- Jun 26  On-Site Training for the 10 Campuses Who Requested It

  • May 20         UND On-Site Training
  • May 22         DCB On-Site Training
  • May 23         BSC On-Site Training
  • May 29         NDSCS On-Site Training
  • June 11         MaSU On-Site Training
  • June 12         WSC On-Site Training
  • June 19         MiSU On-Site Training
  • June 24         VCSU On-Site Training
  • June 25         DSU On-Site Training
  • June 26        LRSC On-Site Training

June 28                  Production Freeze

July 2                      Go-No Go Meeting

Jul 12                     Go-Live Weekend. Production Environment Down at 5 pm Fri, up by noon Mon, July 15th

July 22                    Query Environment will be available (Working to improve date)

July 26                    Backup Go-Live Weekend. Production Environment Down noon Fri – 8 am Monday. Weekend reserved for other potential migration activities.